Accelerating Federal Permitting of Data Center Infrastructure

Signed July 23, 2025, printed at 90 FR 35385. 9 sections of substance, 1,778 words.

In plain English

This order speeds up permits for data centers. It says the country needs them for computing.

Read it at the Federal Register →

Sec. 1. Policy and Purpose

My Administration has inaugurated a golden age for American manufacturing and technological dominance. We will pursue bold, large- scale industrial plans to vault the United States further into the lead on critical manufacturing processes and technologies that are essential to national security, economic prosperity, and scientific leadership. These plans include artificial intelligence (AI) data centers and infrastructure that powers them, including high-voltage transmission lines and other equipment. It will be a priority of my Administration to facilitate the rapid and efficient buildout of this infrastructure by easing Federal regulatory burdens. In addition, my Administration will utilize federally owned land and resources for the expeditious and orderly development of data centers. This usage will be done in a manner consistent with the land's intended purpose--to be used in

My Administration has inaugurated a golden age for American manufacturing and technological dominance. We will pursue bold, large- scale industrial plans to vault the United States further into the lead on critical manufacturing processes and technologies that are essential to national security, economic prosperity, and scientific leadership. These plans include artificial intelligence (AI) data centers and infrastructure that powers them, including high-voltage transmission lines and other equipment. It will be a priority of my Administration to facilitate the rapid and efficient buildout of this infrastructure by easing Federal regulatory burdens. In addition, my Administration will utilize federally owned land and resources for the expeditious and orderly development of data centers. This usage will be done in a manner consistent with the land's intended purpose--to be used in

In plain English

This states the aim. It claims a new age for making things here. It promises large plans in key fields. Data centers for AI are named. So is the power that runs them. Long power lines are named too. It will ease federal rules to speed the build. Federal land may be used.

Sec. 2. Definitions

For purposes of this order: (a) ``Data Center Project'' means a facility that requires greater than 100 megawatts (MW) of new load dedicated to AI inference, training, simulation, or synthetic data generation. (b) ``Covered Components'' means materials, products, and infrastructure that are required to build Data Center Projects or otherwise upon which Data Center Projects depend, including: (i) energy infrastructure, such as transmission lines, natural gas pipelines or laterals, substations, switchyards, transformers, switchgear, and system protective facilities; (ii) natural gas turbines, coal power equipment, nuclear power equipment, geothermal power equipment, and any other dispatchable baseload energy sources, including electrical infrastructure (including backup power supply) constructed or otherwise used principally to serve a Data Center Project; (iii) semiconductors and

For purposes of this order: (a) ``Data Center Project'' means a facility that requires greater than 100 megawatts (MW) of new load dedicated to AI inference, training, simulation, or synthetic data generation. (b) ``Covered Components'' means materials, products, and infrastructure that are required to build Data Center Projects or otherwise upon which Data Center Projects depend, including: (i) energy infrastructure, such as transmission lines, natural gas pipelines or laterals, substations, switchyards, transformers, switchgear, and system protective facilities; (ii) natural gas turbines, coal power equipment, nuclear power equipment, geothermal power equipment, and any other dispatchable baseload energy sources, including electrical infrastructure (including backup power supply) constructed or otherwise used principally to serve a Data Center Project; (iii) semiconductors and

In plain English

This defines terms. A data center project needs more than 100 megawatts of new load. That load must serve AI work. Covered parts are what such a project needs. Power lines and gas pipes count. So do substations and transformers. So do turbines and nuclear gear. Chips count too.

Sec. 3. Encouraging Qualifying Projects

The Secretary of Commerce, in consultation with the Director of the Office of Science and Technology Policy (OSTP) and other relevant executive departments and agencies (agencies), shall launch an initiative to provide financial support for Qualifying Projects, which could include loans and loan guarantees, grants, tax incentives, and offtake agreements. All relevant agencies shall identify and submit to the Director of OSTP any such relevant existing financial support that can be used to assist Qualifying Projects, consistent with the protection of national security.

The Secretary of Commerce, in consultation with the Director of the Office of Science and Technology Policy (OSTP) and other relevant executive departments and agencies (agencies), shall launch an initiative to provide financial support for Qualifying Projects, which could include loans and loan guarantees, grants, tax incentives, and offtake agreements. All relevant agencies shall identify and submit to the Director of OSTP any such relevant existing financial support that can be used to assist Qualifying Projects, consistent with the protection of national security.

In plain English

This tells Commerce to help pay. It works with the science office. Other agencies join in. Loans and loan backing may be used. Grants may be used. Tax breaks may be used. Deals to buy the output may be used. Agencies must report what aid they already have.

Sec. 4.

Revocation of Executive Order 14141. Executive Order 14141 of January 14, 2025 (Advancing United States Leadership in Artificial Intelligence Infrastructure), is hereby revoked.

Revocation of Executive Order 14141. Executive Order 14141 of January 14, 2025 (Advancing United States Leadership in Artificial Intelligence Infrastructure), is hereby revoked.

In plain English

This cancels a January 2025 order. That order dealt with AI sites.

Sec. 5. Efficient Environmental Reviews

(a) Within 10 days of the date of this order, each relevant agency shall identify to the Council on Environmental Quality any categorical exclusions already established or adopted by such agency pursuant to the National Environmental Policy Act (NEPA), reliance on and adoption of which by agencies (pursuant to 42 U.S.C. 4336 and 4336c) could facilitate the construction of Qualifying Projects. (b) The Council on Environmental Quality shall coordinate with relevant agencies on the establishment of new categorical exclusions to cover actions related to Qualifying Projects that normally do not have a significant effect on the human environment. Agencies shall, for purposes of establishing these categorical exclusions, rely on any sufficient basis to do so as each such agency determines. (c) Consistent with 42 U.S.C. 4336e(10)(B)(iii), loans, loan guarantees, grants, tax incentives, or other

(a) Within 10 days of the date of this order, each relevant agency shall identify to the Council on Environmental Quality any categorical exclusions already established or adopted by such agency pursuant to the National Environmental Policy Act (NEPA), reliance on and adoption of which by agencies (pursuant to 42 U.S.C. 4336 and 4336c) could facilitate the construction of Qualifying Projects. (b) The Council on Environmental Quality shall coordinate with relevant agencies on the establishment of new categorical exclusions to cover actions related to Qualifying Projects that normally do not have a significant effect on the human environment. Agencies shall, for purposes of establishing these categorical exclusions, rely on any sufficient basis to do so as each such agency determines. (c) Consistent with 42 U.S.C. 4336e(10)(B)(iii), loans, loan guarantees, grants, tax incentives, or other

In plain English

This speeds up environment reviews. Agencies have 10 days to name their exclusions. Those are reviews they may skip. The list goes to the environment council. That council works with them on new exclusions. New ones cover work with little effect on people. Agencies decide the basis for each.

Sec. 6.

Efficiency and Transparency Through FAST-41. (a) The Executive Director (Executive Director) of the Federal Permitting Improvement Steering Council (FPISC) may, within 30 days of the date that a project is identified to FPISC by a relevant agency, designate a Qualifying Project as a transparency project pursuant to 42 U.S.C. 4370m-2(b)(2)(A)(iii) and section 41003 of the Fixing America's Surface Transportation Act (Public Law 114-94, 129 Stat. 1312, 1747) (FAST-41). Within 30 days of receiving such agency notification, the Executive Director may publish Qualifying Projects on the Permitting Dashboard established under section 41003(b) of FAST-41, including schedules for expedited review. (b) In consultation with Project Sponsors, the Executive Director shall expedite the transition of eligible Qualifying Projects from transparency projects to FAST-41 ``covered projects'' as defined by

Efficiency and Transparency Through FAST-41. (a) The Executive Director (Executive Director) of the Federal Permitting Improvement Steering Council (FPISC) may, within 30 days of the date that a project is identified to FPISC by a relevant agency, designate a Qualifying Project as a transparency project pursuant to 42 U.S.C. 4370m-2(b)(2)(A)(iii) and section 41003 of the Fixing America's Surface Transportation Act (Public Law 114-94, 129 Stat. 1312, 1747) (FAST-41). Within 30 days of receiving such agency notification, the Executive Director may publish Qualifying Projects on the Permitting Dashboard established under section 41003(b) of FAST-41, including schedules for expedited review. (b) In consultation with Project Sponsors, the Executive Director shall expedite the transition of eligible Qualifying Projects from transparency projects to FAST-41 ``covered projects'' as defined by

In plain English

This uses a permit law known as FAST-41. A council runs it. Its director may tag a project for tracking. That must happen within 30 days of notice. Tagged projects go on a public dashboard. Review schedules go up with them. The director must then move fit projects to full covered status.

Sec. 7. Streamlining of Permitting Review

(a) The Administrator of the Environmental Protection Agency shall assist in expediting permitting on Federal and non-Federal lands by developing or modifying regulations promulgated under the Clean Air Act (42 U.S.C. 7401 et seq.); the Clean Water Act (33 U.S.C. 1251 et seq.); the Comprehensive Environmental Response, Compensation, and Liability Act (42 U.S.C. 9601 et seq.); the Toxic Substances Control Act (15 U.S.C. 2601 et seq.); and other relevant applicable laws, in each case, that impact the development of Qualifying Projects. (b) The Administrator of the Environmental Protection Agency shall, consistent with the Environmental Protection Agency's statutory authorities, expeditiously identify Brownfield Sites and Superfund Sites for use by Qualifying Projects. As part of this effort, within 180 days of the date of this order, the Administrator of the Environmental Protection

(a) The Administrator of the Environmental Protection Agency shall assist in expediting permitting on Federal and non-Federal lands by developing or modifying regulations promulgated under the Clean Air Act (42 U.S.C. 7401 et seq.); the Clean Water Act (33 U.S.C. 1251 et seq.); the Comprehensive Environmental Response, Compensation, and Liability Act (42 U.S.C. 9601 et seq.); the Toxic Substances Control Act (15 U.S.C. 2601 et seq.); and other relevant applicable laws, in each case, that impact the development of Qualifying Projects. (b) The Administrator of the Environmental Protection Agency shall, consistent with the Environmental Protection Agency's statutory authorities, expeditiously identify Brownfield Sites and Superfund Sites for use by Qualifying Projects. As part of this effort, within 180 days of the date of this order, the Administrator of the Environmental Protection

In plain English

This tells the EPA to speed permits. It covers federal land and other land. It may write or change rules to do so. Clean air rules are named. So are clean water rules. So are two rules on toxic waste and chemicals. It must also find polluted sites these projects could use.

Sec. 8. Biological and Water Permitting Efficiencies

(a) Upon identification of sites by the Secretary of the Interior and the Secretary of Energy as described in section 9 of this order, the action agency, as identified through the process described in the Endangered Species Act (16 U.S.C. 1531-1544) (ESA), shall initiate consultation under section 7 of the ESA with the Secretary of the Interior, the Secretary of Commerce, or both with respect to common construction activities for Qualifying Projects that will occur over the next 10 years at a programmatic level. The Secretary of the Interior and the Secretary of Commerce shall utilize programmatic consultation to ensure timely and efficient completion of such consultation. (b) Within 180 days of the date of this order, the Secretary of the Army, acting through the Assistant Secretary of the Army for Civil Works, shall review the nationwide permits issued under section 404 of the Clean

(a) Upon identification of sites by the Secretary of the Interior and the Secretary of Energy as described in section 9 of this order, the action agency, as identified through the process described in the Endangered Species Act (16 U.S.C. 1531-1544) (ESA), shall initiate consultation under section 7 of the ESA with the Secretary of the Interior, the Secretary of Commerce, or both with respect to common construction activities for Qualifying Projects that will occur over the next 10 years at a programmatic level. The Secretary of the Interior and the Secretary of Commerce shall utilize programmatic consultation to ensure timely and efficient completion of such consultation. (b) Within 180 days of the date of this order, the Secretary of the Army, acting through the Assistant Secretary of the Army for Civil Works, shall review the nationwide permits issued under section 404 of the Clean

In plain English

This covers wildlife and water permits. Interior and Energy first name the sites. Then the lead agency must start a wildlife review. Interior or Commerce takes part. The review covers common building work. It looks ten years ahead at once. The Army must also review its water permits.

Sec. 9. Federal Lands Availability

(a) The Department of the Interior and the Department of Energy shall, after consultation with industry and further in consultation with the Department of Commerce as to the Project Sponsors to which relevant authorizations shall be granted, offer appropriate authorizations for sites identified by the Secretary of the Interior or the Secretary of Energy, as applicable and appropriate for the relevant uses, consistent with 42 U.S.C. 2201, 42 U.S.C. 7256, 43 U.S.C. 1701 et seq., and all other applicable law. (b) The Secretary of Defense shall, pursuant to 10 U.S.C. 2667 or other applicable law and as and when the Secretary of Defense deems it necessary or desirable, identify suitable sites on military installations for Covered Component infrastructure uses and competitively lease available lands for Qualifying Projects to support the Department of Defense's energy, workforce, and mission

(a) The Department of the Interior and the Department of Energy shall, after consultation with industry and further in consultation with the Department of Commerce as to the Project Sponsors to which relevant authorizations shall be granted, offer appropriate authorizations for sites identified by the Secretary of the Interior or the Secretary of Energy, as applicable and appropriate for the relevant uses, consistent with 42 U.S.C. 2201, 42 U.S.C. 7256, 43 U.S.C. 1701 et seq., and all other applicable law. (b) The Secretary of Defense shall, pursuant to 10 U.S.C. 2667 or other applicable law and as and when the Secretary of Defense deems it necessary or desirable, identify suitable sites on military installations for Covered Component infrastructure uses and competitively lease available lands for Qualifying Projects to support the Department of Defense's energy, workforce, and mission

In plain English

This opens federal land. Interior and Energy must talk with industry. They talk with Commerce about who gets what. Then they offer permits for sites they name. The Defense Department must find sites on bases. It may lease them out by bid. The leases serve its own power and mission needs.

Sec. 10. General Provisions

Every order carries this. It is not what the order does.

(a) Nothing in this order shall be construed to impair or otherwise affect: (i) the authority granted by law to an executive department or agency, or the head thereof; or (ii) the functions of the Director of the Office of Management and Budget relating to budgetary, administrative, or legislative proposals. (b) This order shall be implemented consistent with applicable law and subject to the availability of appropriations. (c) This order is not intended to, and does not, create any right or benefit, substantive or procedural, enforceable at law or in equity by any party [[Page 35388]] against the United States, its departments, agencies, or entities, its officers, employees, or agents, or any other person. (d) The costs for publication of this order shall be borne by the Department of Energy. <GRAPHIC(S) NOT AVAILABLE IN TIFF FORMAT> (Presidential Sig.) THE WHITE HOUSE, July 23, 2025.

(a) Nothing in this order shall be construed to impair or otherwise affect: (i) the authority granted by law to an executive department or agency, or the head thereof; or (ii) the functions of the Director of the Office of Management and Budget relating to budgetary, administrative, or legislative proposals. (b) This order shall be implemented consistent with applicable law and subject to the availability of appropriations. (c) This order is not intended to, and does not, create any right or benefit, substantive or procedural, enforceable at law or in equity by any party [[Page 35388]] against the United States, its departments, agencies, or entities, its officers, employees, or agents, or any other person. (d) The costs for publication of this order shall be borne by the Department of Energy. <GRAPHIC(S) NOT AVAILABLE IN TIFF FORMAT> (Presidential Sig.) THE WHITE HOUSE, July 23, 2025.

In plain English

This is the closing clause that nearly every order carries. It says the order does not change what the law already allows. It also says no one can sue to enforce it.