The energy regulator had a rule that held up some approvals. This drops it.

Read it at the Federal Register →

What the Rule Says It Does

The Federal Energy Regulatory Commission (Commission) removes from its regulations a rule that precludes the issuance of authorizations to proceed with construction activities with respect to natural gas facilities approved pursuant to section 3 or section 7 of the Natural Gas Act for a limited time while certain requests for rehearing are pending before the Commission.

This is the rule's own summary, as the Federal Register prints it.

The Orders It Names

The rule names these orders itself. What it does about them is a reading, and none is recorded here.