A new control center is funded, and at least three existing ones must fold into it
What the document says“$1,900,000,000 for necessary actions to construct a new air route traffic control center”
The section provides $1,900,000,000 to build a new air route traffic control center, with no more than 2 percent of that amount used for planning or administration, and requires at least three existing centers to be divested and folded into the new one. A further $100,000,000 funds a realignment and consolidation effort under which at least ten existing centers are closed or consolidated.
What the document actually says“$1,900,000,000 for necessary actions to construct a new air route traffic control center”
The sum is $1.9 billion. It pays to build one new air traffic control center.
No more than 2 percent may go to planning and admin. At least three old centers must close into it. A separate sum closes or merges ten more.
No action is recorded against this proposal. That is not evidence that none has been taken, and nobody has yet read it against the record. See what the tracker does not yet cover.